Half full on a dry day: what our pipes and our power can really take

You have heard it at the coffee shop: the town cannot take new homes because of its pipes. The Town's own reports say otherwise, on a dry day. Here is what they say, where the real limits are, and how I will put the number on one page.

What the Town's own reports say

Start with the rumour, because it comes up at every door: the town cannot take new homes, the plant is full. The Town publishes a report on each plant every year, on its own website. The sewage plant on Main Street East is rated for 13,800 cubic metres a day. Last year it carried 7,064 on an average day. That is about half. The year before, 58 percent. The year before that, 62.

The water plant is rated for 27,275 cubic metres a day. Its busiest day of 2025 treated 8,349. Less than a third of what it is rated for. And in January, council approved 36 townhouses on full municipal services. The report to council raised no capacity problem.

The wires tell the same story for homes. Hydro One's regional plan, published in February, rates the town's main station at 18 megawatts. Our winter load in 2024 was 14.9. Hydro One sees no need for more until 2037. Room for years of new homes.

Sewage plant · average day in 2025, against its 13,800 rating
51%
Water plant · busiest day of 2025, against its 27,275 rating
31%
Main power station · winter load in 2024, against its 18 megawatt rating
14.9 of 18 MW
Sources · Wastewater treatment plant report 2025 · Drinking water summary report 2025 · Hydro One regional plan, February 2026

So on a dry day, on the Town's own numbers, the rumour is wrong.

Where the real limits are

Storms. About five kilometres of our sewers still carry rain and sewage in the same pipe, and one overflow at Cameron and Main lets it into the river in a storm. In nine months of twelve last year, the month's peak day went past what the plant is built for. In 2024 the plant bypassed five times. The Town's own log shows five overflows to the river so far this year, the most since 2020. That is the real sewer limit. It decides where a new street can connect, and what it costs. It is a pipe problem, street by street. The plant itself has room.

DRY DAY THE PLANT one pipe, one flow the plant takes it all at about half STORM THE PLANT THE RIVER rain and sewage, one pipe ABOUT 5 KM OF COMBINED SEWERS · FIVE OVERFLOWS TO THE RIVER SO FAR THIS YEAR
Dry day, storm day. On about five kilometres of streets, one pipe carries the rain and the sewage. In a storm, the surplus goes to the river.

One big factory. The main station has room for homes. A single big industrial load is a different question, and it goes to Hydro One first, with a connection study, before anyone signs anything. The lights. In 2024 our utility's customers averaged 5.59 hours without power. Take out the outages that started upstream, on Hydro One's lines, and the regulator's scorecard shows 2.57. Most of the hours the lights were out came from upstream of our own utility. And a transformer from 1965 is still in service at our main station. Its replacement has slipped a year, to 2027-2028.

The number nobody has printed

Ontario has a rule for exactly this, Procedure D-5-1. It says a municipality should not recommend approval of new development until it has worked out and filed its uncommitted reserve capacity: how much of each plant is already spoken for, and how much is left. Hawkesbury's number is not on the public record. It may sit in a drawer at Town Hall.

UNCOMMITTED RESERVE CAPACITY · HAWKESBURY Water plant Sewage plant The wires Engineer's name Ontario Procedure D-5-1 · the number comes before growth gets approved NOT ON THE PUBLIC RECORD DUE · MY FIRST HUNDRED DAYS
The one page the province's rule asks for. I will put ours where you can read it, with the engineer's name on it.

The study that would produce it is bought. In May, council awarded a water and sewer servicing study for future development, shared with Champlain, for $109,199 before tax. In September it was still being written. Meanwhile the Town's own water financial plan, adopted last year, assumes the town will not grow, and our own utility's five-year plan assumes no new development. That is where the rumour lives.

The Town has had no development charges since September 2025. The old by-law raised about $445,000 in five years, and this month administration recommended not replacing it.

How we got here

2018
The Town's engineers recommend a fourth filter at the water plant.
Sep 2025
The development charges by-law expires on 1 September. It raised about $445,000 in five years.
Jan 2026
Council approves 36 townhouses on full municipal services.
Feb 2026
Hydro One's regional plan rates the town's main station at 18 megawatts, with no need for more until 2037.
May 2026
Council buys the servicing study with Champlain, $109,199 before tax.
Sep 2026
The fourth filter goes to council for award, due by the end of 2027. Administration recommends not replacing the development charges. Over the summer the Town hired an economic development coordinator. The Town's log shows five overflows to the river by 9 September.
Dec 2026
The Canada-Ontario bid for towns without development charges closes at 4:59 p.m. on 2 December. One project per town.

Who controls what

Four hands are on this file.

The Town

The Town owns both plants and every sewer under the streets, and pays for them through your water bill. Council votes the budget, the sewer list and the December bid.

Our own utility

Hydro Hawkesbury runs the poles, the wires and the two stations inside town, and reports to the Ontario Energy Board. The transformer and the outage log are its file. My line on it does not change: no sale, no merger, no study of one, without a public council vote, with the numbers published first.

Hydro One and the province

Hydro One owns the long line that brings the power to town, and its regional plan sets the number for our main station. The province wrote the capacity rule, helps pay for the fourth filter with drinking-water money, and runs the 2 December bid.

Champlain

Champlain pays a share of the water plant's fourth filter and of the servicing study, and holds the land the industrial park plan is about. The capacity number is theirs to read too.

The part nobody campaigns on: the votes

A mayor of Hawkesbury has one vote of seven and writes the budget.

  1. My penCouncil vote The capacity number on one page, in my first hundred days. How many homes and how much industry the water plant, the sewage plant and the wires can take today, with the engineer's name on it. How often the power went out, and why. I bring council the motion for the reserve-capacity statement the province's rule asks for, and I ask our utility, in writing, for its spare megawatts at each station. Then it goes on one page of the Town's website, dated.
  2. ApplicationCouncil vote One project in the 2 December bid, with the price said out loud. There is a Canada-Ontario fund for towns without development charges. It closes on 2 December, one project per town, up to $20 million, and the price is written into it: no development charges on new homes before 2031. I ask council to pick one project already in design and file it before the deadline. The town pays at least a fifth. I say the price out loud because the guidelines do.
  3. Council vote The last combined sewers, dug once. The five kilometres that still carry rain and sewage together go onto the worst-streets-first roads list, so each street is opened once, for the road and the pipe. And the overflow count gets reported every year, beside the roads report card.
  4. Council vote Make the power hold. The outage hours published every year, split into our own wires, Hydro One's lines and the weather. The 1965 transformer's replacement held to 2027-2028. And before the Champlain agreement is signed, a written answer from Hydro One on who feeds the industrial lands and what it costs to connect.
  5. My pen A serviced-land list an investor can read. Every site in town and in the park: water, sewer, power, cost and time to connect. This summer the Town hired an economic development coordinator. That list belongs on that desk, my budget funds the desk, and the park and Main Street are the two files I bring to it first.
2026 2 DEC 4:59 p.m. the bid closes ONE PROJECT PER TOWN UP TO $20 MILLION the town pays at least a fifth THE PRICE, SAID OUT LOUD no development charges on new homes before 2031 Canada-Ontario fund · program guidelines, August 2026
The bid, with its price printed on the front. Council picks the project; I say the price before the vote.

What I cannot promise, and what I will try

I cannot promise a bigger plant. The reports say we do not need one on a dry day. If the study says otherwise when it lands, I will say so, and this plan becomes the expansion case. I cannot promise a river that never sees an overflow: that is five kilometres of pipe, dug street by street, over more than one budget. And I cannot promise a jobs number, because the capacity number comes first. What I will try: the number in public within a hundred days, one project in the 2 December bid, the sewers on the roads list, the outage hours in the open. All of it at council, in public, four votes of seven.

In my trade you measure before you cut. This town has argued about its pipes for years without the measurement. I will get it, print it, and then go sell what it says.

Prove the capacity. Then sell it.

Denis Pirollo
businessman, entrepreneur, visionary
Building a stronger Hawkesbury together.

The receipts

  • Wastewater Treatment Plant Annual Performance Reports 2024 and 2025, Town of Hawkesbury · the plant's rating, the average and peak flows, the bypasses, the combined sewers and the Cameron and Main overflow.
  • Drinking Water System 2025 Summary Report, Town of Hawkesbury, 28 January 2026 · the water plant's rating, its permit to take water and its busiest day.
  • The Town's overflow log · hawkesbury.ca, Drinking Water and Wastewater Management page, read 23 September 2026 · the five overflows of 2026.
  • Hydro One, Greater Ottawa Regional Infrastructure Plan, 9 February 2026, Table 7-2 · the station's rating, the 2024 load and the 2037 need.
  • Ontario Energy Board scorecards for Hydro Hawkesbury, 2024 and 2025; Hydro Hawkesbury Distribution System Plan 2025 (file EB-2024-0031) · the outage hours, the 1965 transformer and the no-growth assumption.
  • Water System Financial Plan 2025-2035, Town of Hawkesbury, adopted 23 June 2025 · "no customer growth".
  • Ontario Ministry of the Environment, Procedure D-5-1, "Calculating and reporting uncommitted reserve capacity at sewage and water treatment plants" (ontario.ca) · the reserve-capacity rule.
  • Town of Hawkesbury council · 11 May 2026, resolution R-78-26, the servicing study; 28 January 2026, recommendation 2026_REC_01, the 36 townhouses; 14 September 2026, recommendations 2026_REC_50 (the fourth filter) and 2026_REC_51 (the development charges by-law).
  • Municipal Housing Infrastructure Program, Non-Development-Charge Municipalities Stream, program guidelines, August 2026 · the 2 December deadline, one project per municipality, up to $20 million, at least 20% local, no residential development charges before 31 March 2031.
  • Town of Hawkesbury, monthly report to council, September 2026 (14 September agenda) · the economic development coordinator.